![]() |
. |
Eagle Harbor Superfund Site Click Here for Adobe PDF version of this page. |
|||||
|
The Eagle Harbor West Operable Unit NPL Site remediation involved the mitigation of contaminated sediments and upland soil contamination by dredging, excavation, treatment and placement of material within a confined disposal facility constructed onsite. Soils were impacted with lead and mercury associated with paint and blasting grits utilized in the repair and maintenance of ships during and after World War II. Upland
soils were excavated, cement stabilized in Wilder’s pugmill plant and
placed onsite in a one-acre, confined disposal facility.
A groundwater intercept and diversion trench was installed to
eliminate intrusion to the placed material. Two 10,000-gallon
diesel/bunker and one 2,000-gallon gasoline underground storage tanks
were also removed.
Approximately 1,000 tons of TPH contaminated soil were hauled and
disposed of in a subtitle D landfill.
Highly
contaminated marine sediments were removed by clamshell dredging to
depths in excess of 30 feet and placed within an onsite disposal
facility designed to accommodate tidal influences.
Because of the non-leaching characteristics of the heavy metals
in marine conditions, the disposal facility design allows for seawater
to infiltrate into the cell, thereby maintaining the non-leaching
properties of the sediments, but restricts the exfiltration of seawater.
Sediments with lead and mercury concentrations in excess of the
site action levels, but less than the removal criteria, were isolated
and contained by in-place capping.
Both thin and thick layer caps were constructed as dictated by
heavy metal concentrations.
All upland and CDF placement area surfaces were completed to
final grade with imported buffer material and the installation of an
impermeable asphalt cap. The
project was constructed from May to October of 1997 in close
coordination with Washington State Ferries’ maintenance facility
adjacent to, and sharing, the site.
The U.S. Environmental Protection Agency oversaw the project.
The State of Washington Departments of Fisheries, Transportation,
Ecology, and
Natural Resources formed the Technical Steering Committee to
coordinate governmental interests and responses during this privately
funded Superfund action.
Wilder achieved all EPA mandated deadlines and milestones well
ahead of schedule.
Upon completion of site remediation, the site was capped with
asphalt and turned over to the Washington State Ferries for use in
on-going operations. Last updated March 20, 2002 |
|||||||
| . | ![]() |
||||||
|
|
|||||||