ALASKA PROJECTS
EVERGREEN AVENUE
GALENA AIRPORT
KINCAID ESTATES
MOBILITY TEST COMPLEX
WHITE'S CROSSING
NW PROJECTS
CAMPUS GLEN
LUNDEEN PARKWAY
NORMAN BRIDGE
SR20 FALL CREEK
SR166 SLIDE
 
 
 
 
 
Projects - Norman Bridge Emergency Removal

Project Name: Norman Bridge Emergency Removal
Location: Middle Fork Snoqualmie River, King Country, WA
Client: King County
Schedule: August 2004 to November 2004
Awards:

The Project:
On July 8th, 2004, Wilder Construction turned in the winning bid for the emergency removal of the Norman Bridge on the Middle Fork of the Snoqualmie River. One week later, Wilder went to work, faced with the challenge of heavy rains, record setting water flow and an unsafe structure.

“Old Rickety,” as the bridge was known by locals, was a timber truss bridge with a 174.5 foot span that was built in 1950. After a new concrete bridge was built in 1984, the Norman Bridge became unnecessary and was designated for foot traffic only in 1997. In 2000, a horse partially fell through the rotting decking and King County decided to step in, closing the bridge to all traffic. By 2004, the bridge had fallen into such a poor state that King County officials felt its immediate removal was necessary.


Project Challenges:
The emergency removal of the Norman Bridge had to be done quickly. Wilder needed to come up with the method, satisfy a scrupulous client, do it under a compressed schedule to avoid the imminent spawning salmon runs; and do it safely. The day before Wilder went to work, the sky opened and it rained so hard that the river rose 5 feet overnight, setting a 62 year record for stream flow.

Wilder installed erosion control measures, a plastic containment system to catch any pollutants from the deck demolition and a trolley system to move the deck sections to the end of the truss for removal. Then Wilder went to work, removing the failing bridge and any chance of people getting hurt by walking on it.

As the project marched on, Wilder employed a 90 ton hydraulic crane, then a 180 ton, and finally at a critical juncture toward the project’s completion, a 300 ton crane, to remove the final components of the bridge.