Physical
Description of Cap: The
Dover AFB site, known as the Lindane Source Area, was divided into
three areas for capping, see Figure 1. Approximately one-half of
the site was paved with conventional asphalt concrete normally specified
by Dover AFB for road paving. Of the remaining portion approximately
one-half was capped using four inches of dense graded MatCon and
one-half using MatCon with leak detection.

The
leak detection system consists of two impermeable layers of MatCon
with an open-graded (permeable) layer of MatCon sandwiched in-between.
The permeable layer was installed to provide a space and pathway for
fluids to be collected and directed to a sump for detection.
The leak detection
system was constructed using a four-inch thick base layer of impermeable
MatCon sloped to drain to the Northeast corner. An open-graded layer
was placed on top of the base layer in four sections (pads), see
Figure 2. Plastic pipes were placed into the Northeast corners of
each open graded pad to direct fluids to sumps that will be installed
along the north edge of the cap. The areas between and around the
open-graded pads were filled-in using impermeable MatCon to form
barriers isolating the open-graded pads from each other and the
edges of the cap. A four-inch thick layer of MatCon was then placed
over the drainage pads and barriers.
The four-inch
thick section of impermeable MatCon was installed after construction
of the three-layer section.
Construction:
Wilder furnished the modified asphalt binder to local asphalt
producer, Tilcon who manufactured the asphalt concrete and provided
it to paving contractor Ralph Cahill & Son who performed the
installation of the cap. MatCon binder was delivered to Tilcon's
local asphalt plant in tanker trucks. The binder was loaded into
heated storage tanks that had been drained free of Tilcon's standard
asphalt binder. A load of gravel was run through the production
process without any asphalt binder to clean the asphalt plant. MatCon
was then produced in the plant using the specified gradation of
aggregate, MatCon binder and standard asphalt production procedures.
Cahill delivered
the MatCon to the project site in standard end-dump trucks timed
to keep material laydown continuous while minimizing truck wait
times at the site. The MatCon was installed using a conventional
asphalt-paving machine. Each MatCon lift was placed at full depth
to produce a four-inch compacted cover. Placement proceeded in continuous
10-foot wide strips running east to west starting along the north
edge of the site, see Figure 3. This laydown sequence assured that
all joints would be hot within each MatCon section of the cap.
A 10-ton vibratory
compactor followed the paving machine using both vibratory and non-vibratory
passes over the mat. Density testing was performed after compaction
using a Troxler Nuclear density Gauge. The density gauge was calibrated
to provide a percentage of total compaction reading. The roller
performed additional passes over the mat until the density was at
least 97% to correspond to less than 3% air voids in the MatCon.
Quality control testing was performed at both the plant and at the
site.


Testing and
Analysis: As part of the SITE demonstration program, the EPA
will design and perform tests on the completed cover and material
samples taken from the cover to assess applicability of the technology
to various uses as a cover and as a liner system. The EPA will publish
results upon completion of their testing. Any preliminary test results
or interim reports issued by the EPA will be added to this site
as we receive them.
Wilder took
its own samples from the site and performed tests on them. Test
results from an independent certified lab were less than 1 x 10-8
cm/sec permeability for the dense graded MatCon. Wilder also demonstrated
the flow characteristics of the drainage layer during construction
by running a full flowing stream of water from a 3 inch diameter
hose onto the open graded MatCon mat prior to covering it with the
dense graded layer. The entire stream of water flowed through the
drainage layer with no surface collection of the water.
Conclusion:
This third-party test data met, actually surpassed, MatCon's performance
specifications and RCRA requirements. This project also demonstrated
that MatCon could be successfully applied on an actual Superfund
Site project by a local asphalt concrete supplier and a local qualified
asphalt paving contractor using their own personnel and equipment.